Posts Categorized: Construction Updates

October 2014

During the month of October 2014, major construction activities will include miscellaneous on-site paving, testing and commissioning of the 300 tonne Gantry Crane, erection of mobile shelters and miscellaneous steel building finishes. These activities will include delivery of equipment and materials to the site. Truck traffic to the site is expected to average 10 (ten)… Read more »

September 2014

During the month of September 2014, major construction activities will include paving of the employee parking lot and the various on-site sections, testing, and commissioning of the 300 tonne Gantry Crane, erection of mobile shelters and miscellaneous steel building finishes. These activities will include delivery of equipment and materials to the site. Truck traffic to… Read more »

August 2014

During the month of August 2014, major construction activities will include paving of the employee parking lot and the various on-site sections, outfitting, testing, and commissioning of the 300 tonne Gantry Crane, erection of mobile shelters, steel building finishes, miscellaneous concrete pours, and installation of various site services. These activities will include delivery of equipment… Read more »

July 2014

During the month of July 2014, major construction activities will include paving of the employee parking lot and the various on-site sections, outfitting of the 300 tonne Gantry Crane, steel building erection and finishes, miscellaneous concrete pours and installation of the various site services. These activities will include delivery of various equipment and materials to… Read more »

May 2014

During the month of May 2014, major construction activities will include outfitting of the 300 tonne Gantry Crane, steel building erection and finishes, miscellaneous concrete slab pours and installation of the various site services. These activities will include delivery of various equipment and materials to the site. Truck traffic to the site is expected to… Read more »

April 2014

During the month of April 2014, major construction activities will include assembly and erection of the 80 meter high – 300 tonne Gantry Crane, steel building erection and finishes, miscellaneous concrete slab pours and installation of the various site services.  These activities will include delivery of various equipment and materials to the site. Truck traffic… Read more »

March 2014

During the month of March 2014, major construction activities will include continuation of concrete foundation works for the various on-site buildings and structures, steel erection for the various buildings, and the relocation and installation of the various underground site services.  These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and… Read more »

February 2014

During the month of February 2014, major construction activities will include continuation of concrete foundation works for the various on-site buildings and structures, steel erection for the various buildings, and the relocation and installation of the various underground site services. The in-water construction for the Load Out Pier is substantially complete. Remaining work will be… Read more »

January 2014

During the month of January 2014, major construction activities will include continuation of concrete foundation works for the various on-site buildings and structures, steel erection for the various buildings, and the relocation and installation of the various underground site services. In-water construction for the Load-Out Pier is continuing and is restricted within the confines of… Read more »

December 2013

During the month of December 2013, major construction activities will include continuation of concrete foundation works for the various on-site buildings and structures, steel erection for the various buildings, and the relocation and installation of the various underground site services. In-water construction for the Load-Out Pier is continuing and is restricted within the confines of… Read more »

November 2013

During the month of November 2013, major construction activities will include continuation of concrete foundation works for the various on-site buildings and structures, steel erection for the various buildings, and the relocation and installation of the various underground site services. In-water construction for the Load-Out Pier is continuing and is restricted within the confines of… Read more »

October 2013

During the month of October 2013, major construction activities will include continuation of concrete foundation works for the various on – site buildings and structures, steel erection for the various buildings, and the relocation and installation of the various underground site services. In – water construction for the Load – Out Pier is continuing and… Read more »

September 2013

During the month of September 2013, major construction activities will include continuation of concrete foundation works for the various on – site buildings, steel erection for the various buildings, and the relocation and installation of the various underground site services. In – water construction for the Load – Out Pier is continuing and is restricted… Read more »

August 2013

During the month of August 2013, major construction activities will include the continuation of concrete foundation works for the various on-site buildings, steel erection for the various buildings, and the relocation and installation of the various underground site services. In-water construction for the Load-Out Pier is continuing and is restricted within the confines of the… Read more »

July 2013

During the month of July 2013, major construction activities will include continuation of concrete foundation works for the various on-site buildings, steel erection for the various building, and the relocation and installation of the various underground site services. These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials required… Read more »

June 2013

During the month of June, major construction activities will include continuation of concrete foundation works for the various on-site buildings, steel erection for the various building, and the relocation and installation of the various underground site services. These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials required for… Read more »

May 2013

During the month of May, major construction activities will include continuation of concrete foundation works for the various on-site buildings, steel erection for the various building, and the relocation and installation of the various underground site services. These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials required for… Read more »

April 2013

During the month of April 2013, major construction activities will include continuation of concrete foundation works for the various on-site buildings, steel erection for the various building, and the relocation and installation of the various underground site services. These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials required… Read more »

March 2013

During the month of March 2013, major construction activities will include continuation of concrete foundation works for the various on-site buildings, steel erection for the various buildings, and the relocation and installation of the various underground site services. These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials required… Read more »

February 2013

During the month of February 2013, major construction activities will include continuation of concrete foundation works for the various on -site buildings, steel erection for the substation building, and the relocation and installation of the various underground site services. These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials… Read more »

January 2013

During the month of Jan 2013, major construction activities will include continuation of concrete foundation works for the various on-site buildings, steel erection for the substation building, and the relocation and installation of the various underground site services. These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials required… Read more »

November 2012

During the month of December 2012, major construction activities will include concrete foundation works for the new Substation and relocated Maintenance Shop, and relocation and installation of various site services. During the later part of December 2012, the erection of the steel structures for the Substation building will commence. These activities will include delivery of… Read more »

October 2012 – Groundbreaking Ceremony Marks Official Start of $200M Shipyard Modernization Project

For immediate release – October 19, 2012 North Vancouver, BC — A groundbreaking ceremony today at Vancouver Shipyards, in North Vancouver marks a significant milestone in the re -development of the shipyard into a world-class facility that will build a new generation of vessels for the Canadian Coast Guard and Royal Canadian Navy. Construction will… Read more »