During the month of October 2014, major construction activities will include miscellaneous on-site paving, testing and commissioning of the 300 tonne Gantry Crane, erection of mobile shelters and miscellaneous steel building finishes.

These activities will include delivery of equipment and materials to the site. Truck traffic to the site is expected to average 10 (ten) per day.

Hours of work on site is typically 7:00 am to 4:30 pm Monday thru Friday with occasional weekend works required to avoid conflicts with the shipyards operational activities.