November 2012

During the month of December 2012, major construction activities will include concrete foundation works for the new Substation and relocated Maintenance Shop, and relocation and installation of various site services.

During the later part of December 2012, the erection of the steel structures for the Substation building will commence.

These activities will include delivery of concrete and steel structures to the site, with an average of six to ten trucks per week.