January 2013

During the month of Jan 2013, major construction activities will include continuation of concrete foundation works for the various on-site buildings, steel erection for the substation building, and the relocation and installation of the various underground site services.

These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials required for the site services works. Truck traffic to the site is expected to be approximately 8 (eight) per day.

Hours of work on site is typically 7:00 am to 4:30 pm Monday thru Friday with occasional weekend works required to avoid conflicts with the
shipyards operational activities.