February 2014

February 2014

During the month of February 2014, major construction activities will include continuation of concrete foundation works for the various on-site buildings and structures, steel erection for the various buildings, and the relocation and installation of the various underground site services. The in-water construction for the Load Out Pier is substantially complete.  Remaining work will be completed from land. These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials required for the site services work. Truck traffic to the site is expected to be approximately 60 (sixty) per day during the concrete placement dates.

In late February, components for the 300 tonne Gantry Crane will arrive in Vancouver Harbour and delivered to the site via water. Hours of work on site is typically 7:00 am to 4:30 pm Monday thru Friday with occasional weekend works required to avoid conflicts with the shipyards operational activities.