December 2013

During the month of December 2013, major construction activities will include continuation of concrete foundation works for the various on-site buildings and structures, steel erection for the various buildings, and the relocation and installation of the various underground site services. In-water construction for the Load-Out Pier is continuing and is restricted within the confines of the existing shipyard marine structures.

These activities will include delivery of ready-mix concrete, steel structures, and the various pipes and materials required for the site services works. Truck traffic to the site is expected to be approximately 60 (sixty) per day during the concrete placement dates.

Hours of work on site is typically 7:00 am to 4:30 pm Monday thru Friday with occasional weekend works required to avoid conflicts with the shipyards operational activities.