Construction Overview

The construction period is approximately from November 2012 through to October 2014. The majority of the construction works will be within the existing property boundaries of Seaspan.

Miscellaneous works offsite will primarily consist of improvements to the existing parking lot involving paving.

Hours of Work

Construction activities will be in accordance with the construction hours permitted by the District of North Vancouver Regulations.

Generally, hours of work will be Monday thru Friday with some Saturdays from 7:00 am to 4:30 pm. Occasionally, during major concrete pours, hours of work may be extended past 4:30 pm. Sunday works will only be for emergency situations.

Mobilization and demobilization of large construction equipment on and off site will be transported outside of the daytime work hours in order to conform to the condition of the Permit.