During the month of August 2014, major construction activities will include paving of the employee parking lot and the various on-site sections, outfitting, testing, and commissioning of the 300 tonne Gantry Crane, erection of mobile shelters, steel building finishes, miscellaneous concrete pours, and installation of various site services. These activities will include delivery of equipment and materials to the site. Truck traffic to the site is expected to average 15 (fifteen) per day.

Hours of work on site is typically 7:00 am to 4:30 pm Monday thru Friday with occasional weekend works required to avoid conflicts with the shipyards operational activities.