April 2014

During the month of April 2014, major construction activities will include assembly and erection of the 80 meter high – 300 tonne Gantry Crane, steel building erection and finishes, miscellaneous concrete slab pours and installation of the various site services.  These activities will include delivery of various equipment and materials to the site. Truck traffic to the site is expected to average 10 (ten) per day.

The in-water construction for the Load Out Pier is substantially complete.  Remaining works will be completed from land.

Hours of work on site is typically 7:00 am to 4:30 pm Monday thru Friday with occasional weekend works required to avoid conflicts with the shipyards operational activities.